Construction Update April 19th, 2016
Making good progress again this week. The workers are finishing up with the dry wall and sheet rock. Should be ready to paint later this week. Insulation went in upstairs for the storage area. Several bushes and 7 cherry trees were planted in the 90 degree heat (by yours truly) and the entry way has made outstanding process. The roofing is nearly complete and the decorative storefront is nearly completed. A few miscellaneous parts are missing, but coming together nicely. Starting to look like the finished product.