Construction Update June 14th, 2016
Here is the weekly update. With just one week until the move, things are progressing very well. The floors are getting heat welded along the seams currently. The floor in the entry is still being worked on currently. Wainscoting is going up on the walls in reception and the exam rooms and looks great. Plumbing and electrical is making great progress and the surgery lights are hung and ready to use. The reception desk is being installed and looks amazing so far. The lines in the parking lot have been painted and the landscaping is nearly completed. The street side of the building has been painted and the colors look phenomenal. Overall things are getting close to completed. There will be several small things that still need to be finished, but shouldn’t affect our move-in date. Final Inspections are scheduled for Friday and cleaning over the weekend and we should be moving Tuesday (with a few items being moved Monday). Enjoy the weekly pictures, and once again the move in date is still June 21st.