Construction Update May 17th, 2016
Here is the weekly update. Unfortunately we will be delayed two weeks in opening from the floor issues that were found this past week. The portions of the concrete slab that contained oil were cut out (nearly finished today) and are being reinforced today and tomorrow. The plan is to do the pour back on Thursday and the floors will be resumed the following Monday with laying the east half of the building and doing moisture mitigation on the west half. The dog ward’s doors were being installed and a second coat of paint was being applied to the treatment areas and isolation. Hopefully by this time next week the floors will be coming along nicely. Enjoy the pictures. The new anticipated move in date is June 21st, 2016.
Siding
Storefront
Storefront
HVAC Vent Cover
Dog Runs
Dog Ward Door
Dog Ward Door
Lab Floor cutting
Floor Cutting
Kitchen Floor cutting
Floor cutting
Floor cutting
Exam room floor cutting
Reception floor cutting
Floor cutting
Floor Cutting
Reception floor cutting
Storefront
Storefront Entry
Wooden Ceiling
Siding
Siding